All hoses and connections to the cooling system are now in place and the team continues work with sensors and complementary pipe systems for the separation tank. The previously mentioned electrical installation is still in progress and this week the main engine was connected to CASO 005. The last three pictures show, among other things, heat exchangers and the separation tank.

A scedule for test runs and dismantling before exports to Denmark have is also in place now.

 